Wednesday, 23 December 2020

May 2020

 As we got to used to the new norm, I kept going with the stone work. I was now on to the long run down the side of the house which is 15 meters long. With the complication of building onto bed rock so the first course of stone was pegged into the bed rock and bonded as well. 

The addition of 6 inchs to this wall was a 5 day process to laye the stone. It also required about 3 days of sorting stone  to find the larger flat ones and a day of moving the required stone into the hole to be used, which was a journey from the garden at the front of the house and down the ramp at the back. The final day of the process was to spend another day bringing in the back fill (the stone that is packed into the back of wall), all the way around the house again and packing this into the wall as tight as possible.



































April 2020

 As April rolled on and the covid situation started to show that it was not going to be over quickly, it was time to take a re-look at the plan. We had planned for my brother to head down and finish the drive way, build the fence to the club and leave me with the dry stone walling to do after we had riddled the stone pile at the front to take out the excess soil.

So instead I decided to set about the dry stone walling and do sorting and riddling by hand as now everything was closed so we couldn't hire any equipment.

















Tuesday, 22 December 2020

March 2020

 The weather started to improve over the month of March, and world events changed how we were going to think about the work ahead.

Not knowing how long this would go on for I set about finishing off a few jobs that just needed one person - the drains. We needed a breather pipe to the cess pit and to seal off the old drains. Digging in our ground is not that easy, so another slow job.






Winter 2020

 In January and February the work continued on the inside of the house. Mainly sorting out the return and opening of the many boxes we had in storage. We also did some work to tidy up in the garden on good days and processing the last of the paper work for the Passivehause  certification.

As it is winter we managed some snowboarding too.




Friday, 18 December 2020

December 2019

December was getting too cold for outside work. So I moved on to inside jobs which was to produce a bit of art which would give us somewhere to do physio exercises.

Other jobs where not very photographic, but included the spreadsheet for the build costs being bought up to date.









November 2019

 November was to carry on with a winter theme, with us seeing our first snow of the season. The wall at the front was slow going, as sorting of the stone was taking a lot longer due to wet weather and the fact it had some soil in  the stone pile from the building of the front wall. This is all being done by hand so I can  sort out the flat stones as I go. The bonus however was that I found a five pound coin.

 The car finally made it into the garage for the first time which is great when there are early morning runs to the railway station.














October 2019

October was a month of challenging weather. This is the time of year that winter is starting.
So I started to prepare the ramp into the under croft by building a small wall to one side. I started the wall by the front door too. Also had a 'man with a digger' for couple of hours to 'find' the driveway again so we could get the car a little bit further down the drive.
We also managed to find a chair for the lounge too, just need to buy a second one now!