Wednesday 7 November 2018

October 2018

This month has been another busy month with the building doors for the bedrooms, letting the renders finish the last of the house. getting the final coat on wax on the floor and some decorating too













September 2018

Once again sorry this is bit late.
Ok this month was once again working on stone work to it final height so the rendering could be done down on the cap over the stone work.
we also managed a bit of work on the inside while the rendering was being done. this was the Ash flooring was done on the bedrooms














August 2018

Sorry this post has been a bit late. Have been having IT issues which is not helped by rural board band which makes everything a bit slower.
This month has been about stone work again. We have kept going for long enough to get the stone high enough for scaffolding.
Also had the timber floor delivered so that is can start acclimatising to the house. 










Wednesday 8 August 2018

July 2018

This has been a busy month working on the lower section of the house. 10 days were spent on the stone splitter getting a face on the stone. The remainder of the month has been spent working the stone walls up., finishing bathrooms. At the start of the month cooking for scout Network camp.




















Tuesday 31 July 2018

June 2018

June was very much a chance for a change, It had always been in the build plan to have a holiday so we managed to continue our cycle ride around the coast line of Europe heading from Malaga to Nice. I thought I would  add just a few photos of this to the blog. we covered about 1200 miles in total and had a relaxing time. when we came back to was back to getting the rain water drains in building on to the stone work.